Major Water Pipe Work To Start
Written by HFM News on 10th April 2019
Work to lay three miles of new water pipes across Market Harborough is about to start and a full timetable of the works has now been released to Hfm.
The first phase of the year-long project by Severn Trent, costing £2m will be on Rockingham Road – between the railway bridge and Valley Way, which is expected to take just over two months.

Map showing where the pipes will be replaced
Preparation work for that began today, with a site office, barriers, signs and health and safety equipment set to be put in place over the next few days
At the end of April it will start on Kettering Road, which will be made one-way to traffic until August, before it returns to Rockingham Road, where it will be shut to traffic for seven weeks at the railway bridge.

There was a major burst on The Broadway earlier this year
In September new pipes will start being laid in the Clarence Street area, with the final work taking place on Roman Way and Doddridge Road and Western Avenue early next year.
The firm hope the work will reduce the number of burst pipes and leaks.
A timetable of the works is below, although is subject to change:
| Phase | Road name | Draft-Start date | Draft -End date | TMA | Comments |
| Phase 1 | Rockingham Road | 10-04-19 | 19-06-19 | Signs and Barriers | |
| Braybrooke Res (alongside A6 in fields) | 29-04-19 | 29-06-19 | Work in fields alongside A6 | ||
| Kettering Road | 29-04-19 | 13-08- 19 | Road Closure – Multiway traffic lights | Junction Closures(in sections as we work along the road) and a one way closure | |
| section of Rockingham Road onto Great Bowden Road | w/c 10/06/2019 | 27-09-19 | Road Closure – Multiway traffic lights | A section of Great Bowden Road will be closed but access will still be available for the train station and residents | |
| Phase 2 | Private land between Kettering and Rockingham Road | 07-08-19 | 16-08-19 | Signs and Barriers | |
| Kettering Road | 12-08-19 | 30-08-19 | Signs and Barriers – Multiway traffic lights | ||
| Rockingham Road (outside station) | 12-08-19 | 27-09-19 | Road Closure – Multiway traffic lights | ||
| Phase 3 | Clarence Street | 23-09-19 | 15-11-19 | Road Closure – Multiway traffic lights | |
| Fernie Road | 30-09-19 | 25-10-19 | Road Closure – Multiway traffic lights | ||
| Phase 4 | Albert Road | 29-10-19 | 22-11-19 | Road Closure – Multiway traffic lights | |
| Phase 5 | Western Avenue | 18-11-19 | 10-01-20 | Signs and Barriers – Multiway traffic lights | |
| Connaught/Broadway | 25-11-19 | 06-01-20 | Road Closure – Multiway traffic lights | ||
| Phase 6 | Western Avenue | 06-01-20 | 28-02-20 | Road Closure – Multiway lights | |
| Roman Way | 07-01-20 | 10-02-20 | Road Closure – Multiway traffic lights | ||
| Phase 7 | Doddridge Road | 11-02-20 | 09-03-20 | Road Closure – Multiway traffic lights |